This project includes the removal and replacement of deteriorated concrete pavement and curb and gutter at various locations on Chester Drive between Landwehr Road and Miller Drive. The construction contract for this project has been awarded to Schroeder & Schroeder Inc. of Skokie, Illinois.

This project will be completed in six (6) stages (see Construction Staging Plan below). Each stage is estimated to last between 7 and 10 days, weather permitting. During construction of all six (6) stages, only one way eastbound traffic will be permitted on Chester Drive. Westbound traffic will be detoured to Miller Drive. Access to homes via driveways will be interrupted for approximately 7 to 10 days while construction staging/work is occuring in front of the driveways. Parking will be limited. On street parking will be allowed in designated areas.

Please see posts below for project updates.

Friday, September 2, 2011

Schroeder & Schroeder (contractor) has completed Stage 6 (final stage) of the concrete replacement project. This week, Schroeder & Schroeder is completing parkway restoration and punch list work.

Friday, August 26, 2011

Schroeder & Schroeder (contractor) has completed Stage 6 (final stage) of the concrete replacement project. Late this week or early next week, Schroeder & Schroeder is scheduled to begin parkway restoration.

Friday, August 19, 2011

Next week, Schroeder & Schroeder (contractor) will start work on Stage 6 (final stage) of the concrete replacement project. The south side of Chester Drive from Landwehr Road to #4119 Chester (at Miller Drive intersection) will be closed for seven days while the pavement is replaced. Residents are being asked to park east of #4119 Chester Drive or on Miller Drive.

Friday, August 12, 2011

Next week, Schroeder & Schroeder (contractor) will start work on Stage 5 of the concrete replacement project. The north side of Chester Drive from Landwehr Road to #4119 Chester (at Miller Drive intersection) will be closed for seven days while the pavement is replaced. Residents are being asked to park east of #4119 Chester Drive or on Miller Drive.

Friday, August 5, 2011

Next week (starting Monday, August 8th), Schroeder & Schroeder (contractor) will start work on Stage 4 of the concrete replacement project. The north side of Chester Drive from #4119 Chester (at Miller Drive intersection) to #3943 Chester Drive will be closed for seven days while the pavement is replaced. Residents are being asked to park on the north side of Chester Drive east of #3943 Chester Drive during this stage. Parking will also be allowed on Miller Drive and Willow Lane.

Friday, July 29, 2011

Stages I and II of the Chester Drive concrete replacement project are complete. Stage III work will begin Monday, August 1st at 7:00 A.M. The south side of Chester Drive, from 4119 Chester Drive (at Miller Drive intersection) east to 3943 Chester Drive, will be closed for seven days while the pavement is replaced. Therefore, residents on the south side of Chester Drive need be out of their driveways by 7:00 A.M. Monday, August 1st and are asked to park on the south side of Chester east of 3943 Chester during this stage. Parking will also be allowed on Miller Drive and Willow Lane. Residents on the north side of Chester will still have access to their driveways during this stage. We have notified the Glenview Police Department and tickets will not be issued for parking on the street in these areas during the duration of the project.

Chester Drive will be a one-way street, eastbound, for the duration of the project.